The new Central Coast Campus under construction in Gosford has achieved significant milestones throughout 2024.
During the year, the project saw the demolition of the old Mitre 10 site, completion of bulk excavation and ground floor slabs, finishing structural first-floor slab and lift/fire stair cores to roof level, and the start of timber installation.
Next year, the project team will be busy with the next phases of the project, including façade & roof installation, upgrading nearby power infrastructure for site connection, installing building plumbing and electrical services, building internal walls and ceilings, landscaping, and completing final finishes and checks.
The $67 million Central Coast Campus project is jointly funded by the Australian Government, NSW Government, and the University of Newcastle.
Quotes attributable to Federal Member for Robertson, Dr Gordon Reid MP:
“Central Coast Campus in Gosford is an exciting project that will provide a range of study options to our community once completed.
“The campus is helping reinvigorate Gosford and build on its rejuvenation.
“This new campus will create a vibrant presence that empowers students and enriches the Central Coast community with opportunities for growth and success.
“I commend the University of Newcastle on its commitment to Gosford and our region and thank all the hardworking construction workers who have contributed to this project throughout 2024.
“I look forward to construction finishing in the second half of 2025, and the campus being operational in 2026.
Quotes attributable to State Member for Gosford, Ms Liesl Tesch MP
“Gosford is coming alive! The Central Coast campus in Gosford will mean Coasties will have more educational pathways right here on the Central Coast.
“Looking around Gosford, it is clear to see the significant growth of the area, and this is a fantastic opportunity to have the University right in the heart of our city.
“As a University of Newcastle alumni, I am glad to see that the Campus is coming along smashingly and I will be glad to see the Campus operational in 2026, Ms Tesch said.
Located at 305 Mann Street, just 450 metres from the Clinical School and close to Gosford train station, this world-class campus will be a hub for students to study, build skills, and connect with the heart of the city, community, business, and industry.
The new campus is designed to achieve a six-star ‘Design and Built’ Green star rating, featuring versatile teaching and learning spaces.
ENDS